          Major milestone reached as Mt Messenger bypass tunnel construction is completed

          Major milestone reached as Mt Messenger bypass tunnel construction is completed
          Tony Skilling

          Tony Skilling

          2 February 2026

          Bypass MilestoneRoading Taranaki
          The Te Ara o Te Ata Mt Messenger Bypass has marked its most significant milestone yet with the official breakthrough and completion of the project's 235-metre tunnel.

          The long-awaited Te Ara o Te Ata Mt Messenger Bypass has reached its most significant milestone yet with the official completion of the project’s 235m tunnel.

          Tunnelling teams marked the breakthrough on 28 January, successfully finishing the excavation and lining of the structure. It’s a massive win for the project, which aims to fix one of the most notorious sections of State Highway 3.

          The 9m-high tunnel is a first for New Zealand engineering. Because the “papa” sandstone of the mountain is soft and unpredictable, crews had to apply the permanent concrete lining as they dug, rather than waiting until the end.

          For Taranaki locals, this means the end is finally in sight for the winding, steep, and often dangerous climb over the existing summit. The new route will offer a far more reliable connection to the north.

          With the tunnel finished, the skyline at the top of the mountain is about to change. The massive cableway, which has been a landmark for travellers since 2022, is now being decommissioned.

          The cableway was a necessity for moving heavy machinery into the remote, inaccessible valleys where a standard road couldn’t reach. Now that the tunnel is open, the team can simply drive gear through the mountain to reach the northern work zones.

          Removing the cableway is no small task. A specialist crew from Austria will arrive in March to help lower the 60mm main cable using a temporary 18m tower and several cranes. The process is expected to take about six weeks.

          Work is also ramping up on the project’s 125m bridge. Earthworks for the concrete supports are finished, and the focus has shifted to the south pier. The bridge uses angled “legs” designed specifically to protect the wetland and Mimi Stream below.

          Deep under the new road, the team is also installing nearly 100 giant concrete pipes. These culverts aren’t just for drainage; they include special “fish passages” to allow native aquatic life to move through the area undisturbed.

          Mt Messenger Mt Messenger Bypass SH3 Te Ara o Te Ata State Highway 3 NZ Transport Agency

          More Stories

          Waitara High School to Receive Two New Classrooms in Government Funding Round
          School Funding

          Waitara High School to Receive Two New Classrooms in Government Funding Round

          Waitara High School is set to receive two new classrooms as part of a $32.8 million Government property investment aimed at easing roll growth pressures across New Zealand.

          Tony Skilling1 week ago
          Taranaki Alliance Secures $3 Million Government Grant to Support Engineering Sector Pivot
          Regional Grant

          Taranaki Alliance Secures $3 Million Government Grant to Support Engineering Sector Pivot

          A $3 million Regional Infrastructure Fund grant has been awarded to the Taranaki Alliance to help local engineering and manufacturing firms transition away from the oil and gas sector.

          Tony Skilling1 week ago
          Photos: Queen Street Cenotaph pedestrian space complete
          Photos

          Photos: Queen Street Cenotaph pedestrian space complete

          The new pedestrian space around the Queen Street Cenotaph is complete, with seating, planting and safety improvements in place.

          Tony Skilling2 weeks ago
          State Highway 3 Reopens Under Stop-Go Management Following Mt Messenger Slip
          Roading Update

          State Highway 3 Reopens Under Stop-Go Management Following Mt Messenger Slip

          State Highway 3 has reopened under stop-go traffic management south of the Mt Messenger Tunnel following a large slip.

          Tony Skilling2 weeks ago
          New Plymouth District Council and Wai Hononga seek feedback on engagement policies
          Public Consultation

          New Plymouth District Council and Wai Hononga seek feedback on engagement policies

          New Plymouth District Council and Wai Hononga Water Services are calling for public feedback on draft policies that determine how the community is consulted on major decisions.

          Tony Skilling2 weeks ago
          Work Begins on SH3 Awakino Gorge Rebuild to Restore Two-Lane Access
          Roading Update

          Work Begins on SH3 Awakino Gorge Rebuild to Restore Two-Lane Access

          Work has started on rebuilding a section of State Highway 3 through the Awakino Gorge, with the goal of restoring two-lane access by mid-December following severe storm damage.

          Tony Skilling2 weeks ago
          Methanex to indefinitely idle Taranaki production facilities in early 2027
          Economic Blow

          Methanex to indefinitely idle Taranaki production facilities in early 2027

          Methanex Corporation has announced it will indefinitely idle its New Zealand production facilities in early 2027, dealing a major blow to the Taranaki economy due to declining natural gas availability.

          Tony Skilling2 weeks ago
          Port Taranaki reports $13.11m profit but warns of future trade drop
          Business News

          Port Taranaki reports $13.11m profit but warns of future trade drop

          Port Taranaki has posted a $13.11 million net profit for the 2025-26 year but warns of a tough future with trade volumes forecast to halve due to shifts in the region's energy sector.

          Tony Skilling2 weeks ago
          Summer roadworks planned for State Highway 43 as storm repairs wrap up
          Roading Update

          Summer roadworks planned for State Highway 43 as storm repairs wrap up

          NZTA Waka Kotahi is shifting its focus to long-term resilience on the Forgotten World Highway, with summer construction planned to target vulnerable sections.

          Tony Skilling2 weeks ago
          View All Stories