Three massive ammonia storage tanks built in New Plymouth are bound for Australia, showing the strength of Taranaki's heavy engineering sector.
Local firm Dialog Fitzroy constructed the three 100-tonne pressure vessels for Hiringa Energy at a cost of around $3 million. Each tank measures 35 metres long and 3.5 metres in diameter.
PTS Logistics transported the giant vessels through New Plymouth at night this week to Port Taranaki, ready to be shipped across the Tasman.
Standing over five metres high on a 12-axle trailer, each load stretched roughly 56 metres in total length. Driver Jarvis Miller navigated the oversized cargo along SH3 in wet, slippery conditions, even using a bypass ramp originally built in the mid-1980s for the Motunui 'Think Big' project.
"It's a bit of a greasy night, and it's all wet and slippery, so we're hooking up another truck just to give us a little more power over the climb here," Miller told RNZ. He noted that at around 215 tonnes all up, a single truck needed backup to handle the incline, alongside careful suspension adjustments to navigate sharp 90-degree turns without bottoming out.
Once across the ditch, the tanks will be installed at Hiringa Energy's $120 million Good Earth Green Hydrogen and Ammonia project in Moree, New South Wales. Hiringa chief executive Andrew Clennet said the facility will be Australasia's first green fertiliser production plant.
Solar power and battery storage at the Australian site will run an electrolyser to produce hydrogen, which is then combined with nitrogen from the air to create ammonia for the New Plymouth-built bullets. Clennet praised the collaboration with Dialog Fitzroy, telling RNZ the team is also heading over to help lay out the equipment and tie in the pipework.
"Utilising all the expertise that we've developed over years of activity here in Taranaki, bringing in modules from international, and getting really good at placing and them hooking it up, and making sure that's done safely and efficiently, and it works," Clennet said.
Dialog Fitzroy general manager Doug Timanus highlighted how vital these contracts are for keeping skilled tradespeople and apprentices working in the region. He told RNZ competing against Asian manufacturers is tough, making local partnerships crucial for retaining engineering talent in Taranaki and New Zealand.
Did you spot these massive loads moving through New Plymouth this week? Let us know in the comments!